Payday super · AU

Payday super with weekly pays and 30-day progress claims

Last updated 11 September 2026

How contractors can fund payday super on weekly wages while waiting 30 days for progress claim payments, with dates and a worked example.

Site supervisor using a tablet beside workers and construction equipment in moody natural light

Payday super follows the wage payday, not the progress claim. With weekly pays, super must generally reach each worker's fund within 7 business days, even if the head contractor pays your 30-day claim weeks later.

The two payment clocks are separate

This is the part that catches contractors.

You pay the crew every Friday. That Friday is the payday. It starts the super payment clock. The date of your progress claim, assessment, payment schedule or client deposit does not move that deadline.

As at September 2026, the compulsory super guarantee rate is 12%. Payday super has applied since 1 July 2026, and contributions generally need to reach the employee's super fund within 7 business days of payday.

The key word is reach. Sending a file or paying a clearing house is not necessarily enough. The money must arrive at the fund and be accepted within the required period.

Your construction contract runs on another clock. A progress claim might be paid 30 calendar days after the claim, after assessment, or under a timetable set by the contract and the relevant Security of Payment law. Retentions, disputed variations and rejected quantities can push actual cash receipts out further.

None of that pauses payday super.

For a wider explanation of the rules, start with the payday super guide.

A weekly payroll example

Say a subcontractor pays wages every Friday. The payroll has $42,000 of qualifying super earnings for the week.

At 12%, the super amount is:

$42,000 x 12% = $5,040

If wages are paid on Friday 4 September 2026, the contribution would generally need to reach the funds by Tuesday 15 September 2026. That assumes there are no applicable public holidays and each weekday counts as a business day.

The business also submits a progress claim on 4 September with 30-day payment terms. Because 4 October is a Sunday, the customer might not pay until Monday 5 October, depending on the contract.

Here is the mismatch:

Event Example date Cash effect
Weekly wages paid 4 September 2026 Wages leave the bank
Internal target for fund receipt 9 September 2026 $5,040 super leaves or clears
General 7 business day deadline 15 September 2026 Super must generally be at the funds
Expected progress claim receipt 5 October 2026 Customer cash may arrive

In this example, super is due about 20 days before the progress claim cash arrives. The gap can be longer if the claim is assessed down, disputed or paid late.

Four weekly pays at the same level create $20,160 of super. A five-payday month creates $25,200. That is why a monthly allowance based on an average can leave you short.

You can check each pay run using the payday super calculator.

Do not wait for the progress claim

It might feel logical to pay super when the customer pays you. That approach no longer fits weekly payday super.

A better rule is simple: when wages are released, treat the related super as already spent. Move it into a separate payroll account or make the contribution straight away.

Waiting for day 30 creates several risks:

  • The statutory deadline can pass before claim money arrives.
  • A rejected claim can leave no cash for super.
  • A clearing house may take several business days to process the payment.
  • Incorrect member details can cause a contribution to bounce back.
  • A public holiday can reduce the available processing window.
  • Off-cycle wage payments can create another payday and another deadline.

Set an internal target earlier than the legal limit. For example, aim for the funds to receive contributions within 3 business days. That leaves time to correct rejected contributions.

Build super into the weekly cash forecast

A 30-day debtor forecast is not enough. Put weekly payroll and super into the cash forecast as separate lines.

For each expected payday, include:

  1. Net wages.
  2. PAYG withholding.
  3. Super based on qualifying earnings.
  4. Payroll tax, where applicable.
  5. Workers compensation and other labour on-costs.
  6. The expected progress claim receipt date.

Forecast at least the next 8 to 13 weeks. Mark claim receipts as uncertain if they depend on certification, variations or disputed work.

Your forecast should also recognise that not every wage item has the same super treatment. Ordinary hours, some allowances and certain paid leave will commonly attract super. Reimbursements and some overtime amounts may be treated differently. Use the correct earnings classifications in payroll rather than applying 12% blindly to take-home pay or total bank transfers.

Awards, enterprise agreements and employment contracts can also require a higher contribution or an earlier payment pattern. The statutory payday super deadline is not permission to ignore a more favourable employee entitlement.

Give each weekly pay its own audit trail

Weekly payments create more deadlines, so tidy records matter.

For every pay run, keep:

  • the actual date wages were paid
  • each employee's qualifying earnings
  • the super amount calculated
  • the date the contribution was sent
  • the date each fund received and accepted it
  • rejection and refund notices
  • evidence of corrected payments

Reconcile the fund result, not just the clearing house debit. If $5,040 leaves the bank but $480 is rejected because one worker's details are wrong, that worker's contribution has not reached their fund.

New starters and fund changes can involve limited timing rules while details are established. Do not treat those rules as a general extension. Collect choice information during onboarding and validate fund details before the first pay.

Late super can become expensive

As at September 2026, late payday super can trigger the super guarantee charge. The charge can include the unpaid shortfall, a notional earnings amount and an administrative uplift. Under the payday super framework, that administrative uplift can be up to 60%, depending on the circumstances and any available reduction.

Further penalties can apply when an employer does not lodge required information or does not deal with an assessed liability. Directors can also face personal exposure under the director penalty regime.

Do not assume a late contribution fixes everything automatically. A payment can help reduce the remaining liability, but reporting and charge obligations may still apply. If a payment is already late, record the dates, correct it promptly and get advice based on the actual pay run.

A practical routine for contractors

Here is a workable weekly rhythm:

  • Finalise timesheets and qualifying earnings before payroll day.
  • Confirm the super amount while reviewing wages.
  • Reserve the super cash when wages are approved.
  • Submit contributions immediately after payday.
  • Check acceptance before your internal 3 business day target.
  • Fix rejected member payments straight away.
  • Update the 13-week cash forecast for claim delays and retentions.

The main point is not complicated. Price the job and manage cash as if weekly super must be funded from your own working capital. Treat the 30-day progress claim as later reimbursement, not as the source that determines when workers' super gets paid.

More on payday super

The Pay Run newsletter

Join the list, payroll for builders, explained fortnightly.

One email. Unsubscribe anytime. We never share your details.

Questions

Can I pay super when the 30-day progress claim is paid?

Not if that would miss the payday super deadline. The obligation generally follows the date wages are paid. A customer's payment terms, assessment delay or disputed claim does not extend it.

Does the 7 business day period start at the end of the pay week?

It starts from the actual payday, not necessarily the end of the roster or pay period. If the pay period ends Sunday but wages are paid Friday, Friday is the relevant payday.

Is paying a clearing house within 7 business days enough?

Not necessarily. The contribution generally needs to reach and be accepted by the employee's fund within the period. Allow time for clearing house processing, direct debit delays and rejected member details.

What happens in a month with five weekly pays?

You need to fund five separate wage and super cycles. Using the article's example, five weekly super amounts of $5,040 would total $25,200. Build the actual payday count into the cash forecast.

What should I do if a progress claim is disputed and super is due?

Pay the super from available working capital if possible. Do not wait for the dispute to finish. If the payment will be late, correct it promptly and get advice about super guarantee charge reporting and payment obligations.

Construction payroll

Stop reading about it. Put it on your crew.

Published pricing, so you never need a call to get a number. We read your award or agreement and build it, and a walkthrough is there whenever you want one. We reply within one business day.

15 minutes, your EBA, no sales script.

No lock-in · Published pricing · We reply within one business day