EBAs · AU

CFMEU Pattern EBA Clauses That Break Generic Payroll

Last updated 13 November 2026

By Project Payroll team

See which CFMEU pattern EBA clauses cause payroll errors, including weekly super, RDOs, allowances, overtime and redundancy payments.

Payroll worker using a tablet beside a crane and partially built concrete structure on an Australian construction site

CFMEU pattern EBAs break generic payroll because they combine weekly minimum payments, RDO accrual, layered allowances and special overtime rules. The maths is not always hard. The trouble is applying each clause in the right order.

First, there is no single CFMEU EBA

People often talk about “the CFMEU EBA” as if one document covers every construction worker in Australia. It does not.

Pattern agreements can differ by state, employer, project, civil or building work, and the part of the industry involved. Two agreements may look nearly identical but use different allowance rates, increase dates or superannuation wording.

Always start with the executed agreement that actually covers the employer and employee. Check its commencement date, nominal expiry date, classifications, schedules and incorporated documents. Do not copy settings from another builder simply because both agreements use familiar CFMEU wording.

Our EBA payroll hub covers the broader setup issues, including agreement scope, pay increases and payroll testing.

The clauses most likely to cause trouble

Minimum weekly superannuation

A common pattern clause requires a fixed minimum super contribution for a full week. That is different from simply multiplying ordinary time earnings by the statutory super guarantee rate.

The statutory SG rate is 12% from 1 July 2025 and remains 12% as at November 2026. An EBA can still require more. For example, its fixed weekly minimum may exceed 12% of a worker’s ordinary time earnings in a quiet week.

Payroll may need to calculate both amounts and pay the greater one. It must also know what happens during annual leave, personal leave, an RDO, an unpaid absence or a partial first week.

That last part catches people. A payroll system may automatically prorate every weekly amount. The EBA might require a full contribution in some circumstances, a daily fraction in others, or no fixed minimum for a particular absence.

Use the minimum weekly super calculator to test the agreement amount against the percentage calculation. The clause wording still decides the result.

RDO accrual that sits behind paid hours

Many construction agreements arrange a 38-hour week through an RDO cycle. A familiar setup records 7.6 ordinary hours and banks 0.4 hours for each qualifying eight-hour day. But never assume that formula applies to every agreement.

As at November 2026, the National Employment Standards use 38 hours per week as the standard maximum for a full-time employee, plus reasonable additional hours. An EBA may distribute those ordinary hours across a cycle.

Generic payroll can fail when it treats all eight hours as immediately payable ordinary time. It can also fail in the other direction by accruing RDO time on days excluded by the agreement.

You need rules for commencement, termination, public holidays, paid leave, unpaid leave and roster changes. The RDO balance must also reconcile to what appears on the payslip and in the time system.

All-purpose allowances

An all-purpose allowance is not just another line on the payslip. If the agreement says an allowance forms part of the employee’s ordinary rate for all purposes, it may affect overtime, leave, shift penalties and other percentage-based payments.

Say the classification rate is the starting point and an industry allowance is all-purpose. Payroll may need to add that allowance before calculating time-and-a-half or double time. A generic setup often calculates overtime from the classification rate alone, then adds the allowance afterwards. The total will be short.

The exact wording matters. Some allowances are paid for all hours but are not all-purpose. Others apply only while a condition exists, such as height, disability, confined space or particular site work.

Site, project and productivity allowances

Site allowances can depend on project value, location, construction stage or an agreed schedule. Rates may increase on a date that does not match the employee’s classification increase.

That creates separate payroll questions:

  • Which sites attract the allowance?
  • Is it hourly, daily or weekly?
  • Does it apply during leave or an RDO?
  • Does it form part of the overtime base?
  • What happens when an employee works across two sites in one day?

A single permanent allowance attached to the employee record cannot answer all of those questions. The site or job code often has to drive the entitlement.

Daily overtime and weekend rules

Generic payroll likes weekly totals. Construction EBAs often care about when the hours were worked.

The calculation may depend on the daily spread of ordinary hours, work before the rostered start, work after finishing time, Saturday or Sunday work, shiftwork, public holidays and whether overtime continued after a meal break.

Minimum engagements create another trap. A worker may attend for a short period but be entitled to payment for a longer minimum. Payroll needs to compare actual hours with the guaranteed engagement rather than paying clocked time alone.

Do not merge Saturday, Sunday and public holiday rules into one “penalty” code. They may use different multipliers, minimum periods and allowance treatment.

Travel, fares and distant work

Travel clauses may provide a daily fares payment, reimbursement of actual costs, payment for travel time, or special rules for distant jobs and living away from home.

These are different payment types. They can have different tax, super and overtime treatment. The payroll code should reflect what the payment is for, not just call everything “travel allowance”.

The agreement may also distinguish between travelling from home to a nominated site, travelling between sites during paid time, and travelling beyond a defined radius. A generic kilometre field will not handle all three.

Redundancy and income protection contributions

Pattern EBAs may require payments to named redundancy or income protection arrangements. These can be fixed weekly or daily amounts rather than a percentage of wages.

The contribution rules may cover weeks containing paid leave or an RDO. They may also set different treatment for incomplete weeks. These amounts should not be confused with redundancy pay under the National Employment Standards.

The fund remittance needs to reconcile with payroll by employee and contribution period. A total general ledger amount is not enough when a fund rejects or queries an employee record.

Where the calculations diverge

Clause Generic payroll assumption What the EBA may require Common error
Weekly super Pay 12% of ordinary time earnings Pay the greater of SG and a fixed weekly minimum Underpayment in low-hour or leave weeks
RDO cycle Pay every worked hour now Pay ordinary hours and bank part of each qualifying day Wrong RDO balance or duplicated pay
All-purpose allowance Add allowance after overtime Include allowance in the rate before applying the multiplier Overtime calculated on too small a base
Site allowance Attach one rate to the employee Change the rate by project, location or effective date Wrong site rate or missed increase
Overtime Trigger after weekly hours Apply daily, time-band and weekend rules Ordinary hours paid where overtime applies
Redundancy contribution Calculate a wage percentage Pay a fixed amount under the clause or schedule Missing payments for qualifying weeks

Clause order matters

Here is the practical bit. Build the calculation in the same order as the agreement.

First identify the classification and current base rate. Next add any allowance that forms part of the rate for all purposes. Then classify the hours as ordinary time, overtime, shiftwork, weekend work or public holiday work. Apply minimum engagements and payment guarantees. After that, calculate separate weekly obligations such as super, redundancy and income protection.

If payroll applies these steps in another order, each individual pay code can look reasonable while the final gross pay is wrong.

Also keep effective dates against each rate. A classification increase, site allowance increase and fund contribution increase may occur on three different dates. Back pay should reproduce the original hours and conditions, not simply apply a percentage to the employee’s total historical gross pay.

Records need to prove the result

As at November 2026, employers generally must give a payslip within one working day of payment. As at November 2026, employee records generally need to be kept for seven years.

For construction EBA payroll, keep enough detail to rebuild the calculation. That includes timesheets, roster cycles, site allocation, classifications, allowance eligibility, rate tables, leave, RDO movements and contribution files.

Run test cases before a new agreement or rate schedule goes live. Include a normal week, a partial week, an RDO, paid leave, unpaid leave, overtime across midnight, Saturday work, a public holiday and a worker moving between sites.

That is the difference between a payroll setup that merely produces a number and one that can show why the number is right.

More on ebas →

The Pay Run newsletter

Join the list, payroll for builders, explained fortnightly.

One email. Unsubscribe anytime. We never share your details.

Questions

Does every CFMEU pattern EBA require minimum weekly super?

No. The obligation depends on the executed agreement covering the employer and employee. Check the super clause, schedules, contribution amount, partial-week rules and treatment of leave.

Should an all-purpose allowance be included in overtime?

Usually, if the agreement says the allowance forms part of the employee’s rate for all purposes. The exact clause controls which penalties, leave payments and other entitlements use the higher rate.

Can payroll prorate a weekly EBA contribution for a short week?

Only if the agreement permits or requires it. Some clauses set a daily fraction, while others preserve a full weekly amount in specified circumstances. Do not apply automatic proration without checking.

Why do RDO balances often disagree with timesheets?

The time system may record eight worked hours while payroll pays 7.6 hours and banks 0.4 hours. Differences also arise when leave, public holidays or unpaid absences are given the wrong accrual treatment.

How often should CFMEU EBA payroll rules be tested?

Test them before implementation, at every rate or clause change, and after material payroll configuration changes. Use real scenarios covering leave, RDOs, overtime, weekends, site changes and partial weeks.

Construction payroll

Stop reading about it. Put it on your crew.

Crew Time sends approved site timesheets to Employment Hero. Ask about construction setup and award or EBA rebuild consulting, or book a walkthrough.

15 minutes, your EBA, no sales script.

No lock-in · Published pricing · We reply within one business day